Live status / Cloud infrastructure
Latitude.sh has planned maintenance in progress.
Latitude.sh has planned maintenance in progress according to its official source.
Signal updated 2h ago · Sep 17, 2026, 6:35 PM UTC
Current incident · started Sep 17, 2026, 6:31 PM UTC
Ashburn Electrical Maintenance Notice 2
On October 8th - 9th, 2026, starting at 08:00 EDT each day, our Ashburn datacenter provider will upgrade the building's critical power system. The work is performed on one power lineup at a time (about one day each), and affected cabinets will temporarily run on a single power feed. No downtime is expected and no customer action is required, though power redundancy will be reduced during the work. Updates will be posted here.
Affected surface
Components
0 of 36 affected
Official incident text
On October 8th - 9th, 2026, starting at 08:00 EDT each day, our Ashburn datacenter provider will upgrade the building's critical power system. The work is performed on one power lineup at a time (about one day each), and affected cabinets will temporarily run on a single power feed. No downtime is expected and no customer action is required, though power redundancy will be reduced during the work. Updates will be posted here.
Source text is preserved verbatim and paired with its retrieval time.Last 30 days · Status timeline
What changed
- Scheduled
On September 14 - 18, 2026, starting at 07:00 EDT each day, our Ashburn datacenter provider will upgrade the building's critical power system. The work is performed on one power lineup at a time (about one day each), and affected cabinets will temporarily run on a single power feed. No downtime is expected and no customer action is required, though power redundancy will be reduced during the work. Updates will be posted here.
- In Progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
- In Progress
Scheduled maintenance is still in progress. We will provide updates as necessary.
- In Progress
Scheduled maintenance is still in progress. We will provide updates as necessary.
- In Progress
Scheduled maintenance is still in progress. We will provide updates as necessary.
- In Progress
Scheduled maintenance is still in progress. We will provide updates as necessary.
- Scheduled
On October 8th - 9th, 2026, starting at 08:00 EDT each day, our Ashburn datacenter provider will upgrade the building's critical power system. The work is performed on one power lineup at a time (about one day each), and affected cabinets will temporarily run on a single power feed. No downtime is expected and no customer action is required, though power redundancy will be reduced during the work. Updates will be posted here.